CALGARY, Alberta, July 02, 2025 (GLOBE NEWSWIRE) -- NuVista Energy Ltd. (TSX:NVA, "NVA" or "NuVista") is providing revised guidance to our annual production volumes and reiterating our commitment to our shareholder return strategy. Due to continued delays in commissioning the Pipestone Gas Plant (“Pipestone Plant”) and additional required work discovered during a gas plant turnaround in the greater Wapiti area (“Wapiti Turnaround”), we now anticipate annual volumes to average approximately 83,000 Boe/d(1). The impact of the delays due to the Pipestone Plant and Wapiti Turnaround on annual production volumes is approximately 3,500 Boe/d and 6,000 Boe/d, respectively. Both third-party facilities are expected to be fully operational prior to September.
CALGARY, Alberta, June 18, 2025 (GLOBE NEWSWIRE) -- NuVista Energy Ltd. (TSX:NVA, "NVA" or the "Corporation") announces that the Toronto Stock Exchange (the "TSX") has approved the renewal of the Corporation's normal course issuer bid (the "2025 NCIB").